ADU guide · New York, NY

Do I need a permit to build an ADU in NYC?

Updated October 2026

Yes. As of October 2026, every new ADU in New York City is filed with the Department of Buildings through DOB NOW: Build. A unit inside the existing building is an Alteration CO job; a detached unit, or one separated by a firewall, is a New Building job. The finished ADU appears on an updated certificate of occupancy.

Who prepares the filing?

Plans are prepared and filed by a registered design professional, a New York-licensed architect or engineer. DOB reviews pre-approved designs from licensed design professionals for its Pre-Approved Plan Library, and owners who choose one can hire the professional who created it.

What are the main steps?

  1. Eligibility check: building type, zoning district, flood maps, historic and special districts.
  2. Design to the Zoning Resolution and Appendix U of the Building Code.
  3. Filing in DOB NOW as Alt-CO or New Building, with professional certification allowed for most ADUs.
  4. Construction under permit, with inspections.
  5. For basements and cellars, DOHMH radon and vapor certification before a temporary certificate of occupancy.
  6. A new or amended certificate of occupancy noting the ADU.
Floor plan and site plan drawings

What other approvals can apply?

  • LPC review for exterior work in a historic district.
  • Multiple Dwelling Law requirements when an ADU makes a two-family house a three-unit building.

How long does it take?

HPD's guidebook says an ADU can take anywhere from two months to two and a half years from design to completion, and advises planning a flexible timeline. Interior conversions with complete filings tend to be at the short end.

What if I already built something without a permit? It depends on what and when. Existing unpermitted basement and cellar units may fit the Local Law 126 pilot. Other unpermitted work generally has to be legalized through a DOB filing. See the legalization guide.

Sources, as of October 2026:

  • NYC DOB announcement, September 30, 2025, and ADU FAQs.
  • NYC DOB rule 1 RCNY 105-08.
  • NYC HPD, ADU guidebook.